19th century cemetery chapel and mortuary. Brick with ashlar dressings and slate roof. LOCAL LIST
Site Type: Broad
Place of Worship
SITEDESC
19th century cemetery chapel and mortuary. Brick with ashlar dressings and slate roof.
Site Name
Dipe Lane, Cemetery Chapel
Site Type: Specific
Cemetery Chapel
SITE_STAT
Local List
HER Number
15242
Form of Evidence
Extant Building
Sources
SOUTH TYNESIDE LOCAL LIST REVIEW 2011: REFERENCE NUMBER: LSHA/138/B
YEAR1
2012
English, British
Class
Transport
COMP1
Jennifer Morrison
DAY1
21
District
Gateshead
Easting
3102
EASTING2
2833
Grid ref figure
8
LANDUSE
Thoroughfare
Map Sheet
NZ36SW
MAP2
NZ25NE
MONTH1
09
Grid Reference
NZ
NGR2
NZ
Northing
6185
NORTHING2
5428
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Birtley
Description
A 2.5 mile section of dual three-lane carriageway costing £2.3 million. Constructed between July 1968 and April 1970 by Robert McGregor & Sons Ltd. On completion this was the first dual three-lane motorway north of the M1. The scheme was built on the same alignment as the existing Trunk Road A1 dual carriageway by-pass, built in the 1930s. The contract included five bridges, one over a railway. The bridges had spread footings. Four had pre-cast pre-stressed beams. One bridge had steel I beams and was the longest single-span bridge to have been designed by the NERCU (North East Road Construction Unit) Durham Sub-Unit. The span was 150 feet and had a skew of 33 degrees. Each of the 8 beams weighed 30 tons. This bridge carried the north carriageway over the southbound carriageway of the A1(M), being the future link road to the Tyne Tunnel. Two mine shafts were found (12 were shown on the contract drawings, all disused for nearly 100 years). The in-filled shafts were capped by concrete slabs 2 feet thick.
Site Type: Broad
Road Transport Site
SITEDESC
A 2.5 mile section of dual three-lane carriageway costing £2.3 million. Constructed between July 1968 and April 1970 by Robert McGregor & Sons Ltd. On completion this was the first dual three-lane motorway north of the M1. The scheme was built on the same alignment as the existing Trunk Road A1 dual carriageway by-pass, built in the 1930s. The contract included five bridges, one over a railway. The bridges had spread footings. Four had pre-cast pre-stressed beams. One bridge had steel I beams and was the longest single-span bridge to have been designed by the NERCU (North East Road Construction Unit) Durham Sub-Unit. The span was 150 feet and had a skew of 33 degrees. Each of the 8 beams weighed 30 tons. This bridge carried the north carriageway over the southbound carriageway of the A1(M), being the future link road to the Tyne Tunnel. Two mine shafts were found (12 were shown on the contract drawings, all disused for nearly 100 years). The in-filled shafts were capped by concrete slabs 2 feet thick.
Site Name
A1(M) Birtley By-pass
Site Type: Specific
Road
HER Number
15241
Form of Evidence
Structure
Sources
F.A. Sims, 2009, The Motorway Achievement - Building the Network in the North East of England, pp 62-63
YEAR1
2012
English, British
Class
Transport
COMP1
Jennifer Morrison
DAY1
21
District
N Tyneside
Easting
2323
EASTING2
2384
Grid ref figure
8
LANDUSE
Thoroughfare
Map Sheet
NZ27SW
MONTH1
09
Grid Reference
NZ
NGR2
NZ
Northing
7446
NORTHING2
7121
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Wideopen
Description
This 2.7 mile road scheme by-passed the villages of Wide Open and Seaton Burn. It was completed in 1969. The final structure on the diversion is Fisher Lane Bridge at the A1 and A19 junction. The route line had been laid down and protected from development in 1939 following the passing of the Trunk Road Act of 1936. The diversion now links the Newcastle Western By-pass to the dual carriageway section of the A1 between Shotton Edge and Stannington Bridge. The scheme was designed by John Miller. It was built by Higgs and Hill Civil Engineering Ltd. Alderman Sydney Pickup opened the road. In 1995 Blagdon Bridge, designed by David Laux, was opened to remove a junction accident spot.
Site Type: Broad
Road Transport Site
SITEDESC
This 2.7 mile road scheme by-passed the villages of Wide Open and Seaton Burn. It was completed in 1969. The final structure on the diversion is Fisher Lane Bridge at the A1 and A19 junction. The route line had been laid down and protected from development in 1939 following the passing of the Trunk Road Act of 1936. The diversion now links the Newcastle Western By-pass to the dual carriageway section of the A1 between Shotton Edge and Stannington Bridge. The scheme was designed by John Miller. It was built by Higgs and Hill Civil Engineering Ltd. Alderman Sydney Pickup opened the road. In 1995 Blagdon Bridge, designed by David Laux, was opened to remove a junction accident spot.
Site Name
A1 Wideopen to Seaton Burn Diversion
Site Type: Specific
Road
HER Number
15240
Form of Evidence
Structure
Sources
F.A. Sims, 2009, The Motorway Achievement - Building the Network in the North East of England, p 74
YEAR1
2012
English, British
Class
Transport
COMP1
Jennifer Morrison
DAY1
21
District
Gateshead and Newcastle
Easting
2230
EASTING2
2011
Grid ref figure
8
LANDUSE
Thoroughfare
Map Sheet
NZ26SW
MONTH1
09
Grid Reference
NZ
NGR2
NZ
Northing
6946
NORTHING2
6250
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Newcastle
Description
The Newcastle Western Bypass was listed in the Department of Transport's 'Policy for Roads, England 1980' to link the A69 to the A1(M) to the south. The County Council proposed an extension of the bypass to the north. The bypass was opened and the Blaydon Bridge was named by Her Majesty the Queen in December 1990. The scheme was awared to Bullen and Partners. The route was first suggested in 1936 and a corridor was reserved in the development plan for the area in 1945. Housing was built on either side of the corridor. The preferred route was announced in 1981 that linked the Great North Road near Gosforth to Scotswood Bridge. Scotswood Bridge was not in good condition and so Blaydon Bridge was built. The bypass is 11km long. It reduced traffic using the Tyne Bridge and removed much traffic from the City centre. It was designed to carry 50,000 vehicles per day. It is dual carriageway with a third lane between interchanges from Scotswood Road to Ponteland Road. Ten footbridges and subways were built to separate traffic and pedestrians. 1200 homes were noise insulated. Earth bunds and concrete screening walls, trees and shrubs reduce traffic noise. 66 houses were demolished to make way for the road. Where the road crosses the line of Hadrian's Wall, stone setts and a plaque were provided to mark the line of the Wall. The scheme cost some £88 million. The scheme was divided into five contracts. Contract 1 - Etal Lane to North Brunton. Balfour Beatty Construction Ltd. Started in August 1987. Opened to traffic in March 1990 by Robert Atkins MP, Minister for Roads and Traffic. Contract 1A - Fawdon Railway Bridge. Built by Cementation Projects Ltd. The bridge carried the new road over the Metro line at Fawdon. Contract 2 - Blaydon Bridge and Blaydon haughs Viaduct. Built by Edmund Nuttall Ltd. Commenced in November 1987. Blaydon Bridge is a five-span pre-stressed concrete structure. It was built using the balanced cantilever technique. It spans 108m over the River Tyne. The sandstone rock below the riverbed was found not to be strong enough to bear the weight of the southern main pier so mini-piles had to be drilled inside a cofferdam to strengthen the pier foundation. Blaydon Haughs Viaduct is a 17-span steel viaduct carrying the bypass over A695 Chainbridge Road and the Newcastle-Carlisle Railway. It is 530m long and the deck incorporates 2,100 tonnes of steelwork supported on 3,500 tonnes of steel H-piles. Contract 3 - Derwenthaugh to Etal Lane. Balfour Beatty Construction Ltd. Commenced in June 1988. This section includes 7 road bridges, 8 footbridges, 8 subways and over 3km of retaining walls. Old coal mine workings were found. Shallow seams were excavated and filled with compacted soil. Deeper workings were injected with cement and pulverised fuel ash grout. One mineshafts were filled and capped with reinforced concrete.
Site Type: Broad
Road Transport Site
SITEDESC
The Newcastle Western Bypass was listed in the Department of Transport's 'Policy for Roads, England 1980' to link the A69 to the A1(M) to the south. The County Council proposed an extension of the bypass to the north. The bypass was opened and the Blaydon Bridge was named by Her Majesty the Queen in December 1990. The scheme was awarded to Bullen and Partners. The route was first suggested in 1936 and a corridor was reserved in the development plan for the area in 1945. Housing was built on either side of the corridor. The preferred route was announced in 1981 that linked the Great North Road near Gosforth to Scotswood Bridge. Scotswood Bridge was not in good condition and so Blaydon Bridge was built. The bypass is 11km long. It reduced traffic using the Tyne Bridge and removed much traffic from the City centre. It was designed to carry 50,000 vehicles per day. It is dual carriageway with a third lane between interchanges from Scotswood Road to Ponteland Road. Ten footbridges and subways were built to separate traffic and pedestrians. 1200 homes were noise insulated. Earth bunds and concrete screening walls, trees and shrubs reduce traffic noise. 66 houses were demolished to make way for the road. Where the road crosses the line of Hadrian's Wall, stone setts and a plaque were provided to mark the line of the Wall. The scheme cost some £88 million. The scheme was divided into five contracts. Contract 1 - Etal Lane to North Brunton. Balfour Beatty Construction Ltd. Started in August 1987. Opened to traffic in March 1990 by Robert Atkins MP, Minister for Roads and Traffic. Contract 1A - Fawdon Railway Bridge. Built by Cementation Projects Ltd. The bridge carried the new road over the Metro line at Fawdon. Contract 2 - Blaydon Bridge and Blaydon haughs Viaduct. Built by Edmund Nuttall Ltd. Commenced in November 1987. Blaydon Bridge is a five-span pre-stressed concrete structure. It was built using the balanced cantilever technique. It spans 108m over the River Tyne. The sandstone rock below the riverbed was found not to be strong enough to bear the weight of the southern main pier so mini-piles had to be drilled inside a cofferdam to strengthen the pier foundation. Blaydon Haughs Viaduct is a 17-span steel viaduct carrying the bypass over A695 Chainbridge Road and the Newcastle-Carlisle Railway. It is 530m long and the deck incorporates 2,100 tonnes of steelwork supported on 3,500 tonnes of steel H-piles. Contract 3 - Derwenthaugh to Etal Lane. Balfour Beatty Construction Ltd. Commenced in June 1988. This section includes 7 road bridges, 8 footbridges, 8 subways and over 3km of retaining walls. Old coal mine workings were found. Shallow seams were excavated and filled with compacted soil. Deeper workings were injected with cement and pulverised fuel ash grout. One mineshafts were filled and capped with reinforced concrete. Contract 4 - Birse Construction Ltd. A 1km long section of road at Derwenthaugh where 8m high embankments were constructed over deep deposits of soft alluvial silts and clays. Commenced February 1987. Water was drained from the clay through vertical sand drains. 24,000 sand drains were installed (total length of 210km) on a grid layout. Once the ground was stabilised, the road could be built. The work took until August 1987.
Site Name
Western By-pass
Site Type: Specific
Road
HER Number
15239
Form of Evidence
Structure
Sources
F.A. Sims, 2009, The Motorway Achievement - Building the Network in the North East of England, pp 64-72
YEAR1
2012
English, British
Class
Transport
COMP1
Jennifer Morrison
DAY1
21
District
Newcastle
Easting
2491
EASTING2
2519
Grid ref figure
8
LANDUSE
Thoroughfare
Map Sheet
NZ26SE
MONTH1
09
Grid Reference
NZ
NGR2
NZ
Northing
6543
NORTHING2
6398
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Newcastle
Description
A start was made on the Newcastle Central Motorway East in 1972 as a trial Urban Motorway from the north side of the central area eastwards to the Tyne Bridge. This section opened to traffic in 1975 and became part of the Great North Road A6157(M). This was later renumbered as A167(M). The rest of the scheme was abandoned until the late 1980s.
Site Type: Broad
Road Transport Site
SITEDESC
A start was made on the Newcastle Central Motorway East in 1972 as a trial Urban Motorway from the north side of the central area eastwards to the Tyne Bridge. This section opened to traffic in 1975 and became part of the Great North Road A6157(M). This was later renumbered as A167(M). The rest of the scheme was abandoned until the late 1980s.
Site Name
Central Motorway East
Site Type: Specific
Road
HER Number
15238
Form of Evidence
Structure
Sources
F.A. Sims, 2009, The Motorway Achievement - Building the Network in the North East of England, p 64
YEAR1
2012
English, British
Class
Transport
COMP1
Jennifer Morrison
DAY1
21
District
Gateshead and Sunderland
Easting
3103
EASTING2
2839
Grid ref figure
8
LANDUSE
Thoroughfare
Map Sheet
NZ25NE
MONTH1
09
Grid Reference
NZ
NGR2
NZ
Northing
6122
NORTHING2
5653
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Washington
Description
£1.6m contract to improve a section of the A1 to dual carriageway. Now designated A194(M). The work was undertaken by Brimms & Co. Ltd from April 1968 to March 1970. The work included the construction of the Havannah Interchange with the B1288, the Follingsby Interchnage and the A195 Peareth Hall overbridge. The scheme was designed by the Durham County Council Sub-Unit of the NERCU (North East Road Construction Unit).
Site Type: Broad
Road Transport Site
SITEDESC
£1.6m contract to improve a section of the A1 to dual carriageway. Now designated A194(M). The work was undertaken by Brimms & Co. Ltd from April 1968 to March 1970. The work included the construction of the Havannah Interchange with the B1288, the Follingsby Interchange and the A195 Peareth Hall overbridge. The scheme was designed by the Durham County Council Sub-Unit of the NERCU (North East Road Construction Unit).
Site Name
A194 White Mare Pool to Black Fell
Site Type: Specific
Road
HER Number
15237
Form of Evidence
Structure
Sources
F.A. Sims, 2009, The Motorway Achievement - Building the Network in the North East of England, p 63
YEAR1
2012
English, British
Class
Commercial
COMP1
Jennifer Morrison
DAY1
17
District
S Tyneside
Easting
3397
Grid ref figure
8
LANDUSE
Building
Map Sheet
NZ36SW
MATERIAL
Timber
MONTH1
08
Grid Reference
NZ
Northing
6103
General Period
21ST CENTURY
Specific Period
21st Century 2001 to 2100
Place
Boldon Colliery
Description
£5million managed office development. Opened in May 2005. By Ryder architects. Bold and imaginative. LOCAL LIST
Site Type: Broad
Commercial Office
SITEDESC
£5million managed office development. Opened in May 2005. By Ryder architects. Bold and imaginative. The brief was for a building which would act as a symbol of transformation in South Tyneside, a purpose-built managed office building offering 44 offices with support and facilities for start-up and small businesses. The design is a pair of linked cubes, each containing four floors, on a free-form plinth containing a reception, café, information area and meeting spaces. The building had to be sustainable and so it has been built with recyclable low embodied energy materials, including cedar timber cladding, slate and maple. It has energy-conserving heating and lighting systems. Fittings are stainless steel and glass. The complex received an RIBA Award in 2007 and a South Tyneside Good Design Award in 2006.
Site Name
Boldon Colliery, Woodstock Way, Quadrus Centre
Site Type: Specific
Commercial Office
SITE_STAT
Local List
HER Number
15236
Form of Evidence
Extant Building
Sources
SOUTH TYNESIDE LOCAL LIST REVIEW 2011: REFERENCE NUMBER: LSHA/116/B; Carroll, Rutter, 2012, Ryder (RIBA Publishing)
YEAR1
2012
English, British
Class
Commercial
COMP1
Jennifer Morrison
DAY1
14
District
S Tyneside
Easting
3172
Grid ref figure
8
LANDUSE
Building
Map Sheet
NZ36NW
MATERIAL
Brick
MONTH1
08
Grid Reference
NZ
Northing
6564
General Period
20TH CENTURY
Specific Period
Late 20th Century 1967 to 2000
Place
Hebburn
Description
A purpose built eco centre, built in 1996. It incorporates up-to-date sustainable construction methods for the offices and also provides adequate quality tenancies for local start-up businesses, along with support of local jobs, job creation and social enterprise.
Developed by Groundwork South Tyneside, all materials were recycled from sustainable sources, including re-used bricks from a demolished factory, an aluminium roof re-smelted from old drink cans, wood from farmed forests and woollen carpets. Electricity is generated by a wind turbine and photovoltaic display.
This award-winning project has become an exemplar of sustainability. LOCAL LIST
Site Type: Broad
Commercial Office
SITEDESC
A purpose built eco centre, built in 1996. It incorporates up-to-date sustainable construction methods for the offices and also provides adequate quality tenancies for local start-up businesses, along with support of local jobs, job creation and social enterprise. Developed by Groundwork South Tyneside, all materials were recycled from sustainable sources, including re-used bricks from a demolished factory, an aluminium roof re-smelted from old drink cans, wood from farmed forests and woollen carpets. Electricity is generated by a wind turbine and photovoltaic display. This award-winning project has become an exemplar of sustainability.
Site Name
Eco Centre and wind turbine
Site Type: Specific
Commercial Office
SITE_STAT
Local List
HER Number
15235
Form of Evidence
Extant Building
Sources
SOUTH TYNESIDE LOCAL LIST REVIEW 2011: REFERENCE NUMBER: LSHA/110/J
YEAR1
2012
English, British
Class
Commercial
COMP1
Jennifer Morrison
DAY1
14
District
S Tyneside
Easting
3061
Grid ref figure
8
LANDUSE
Building
Map Sheet
NZ36NW
MATERIAL
Brick
MONTH1
08
Grid Reference
NZ
Northing
6481
General Period
POST MEDIEVAL
Specific Period
Victorian 1837 to 1901
Place
Hebburn
Description
Victoria House was Martin’s Bank, before being taken over by Barclays in the late 1960s. At this time the premises were shared by a finance and loan company called Battman & Co. The building now serves the community as a funeral home. Brick with ashlar detail. LOCAL LIST
Site Type: Broad
Bank (Financial)
SITEDESC
Victoria House was Martin’s Bank, before being taken over by Barclays in the late 1960s. At this time the premises were shared by a finance and loan company called Battman & Co. The building now serves the community as a funeral home. Brick with ashlar detail.
Site Name
7-9 Prince Consort Road, Victoria House
Site Type: Specific
Bank (Financial)
SITE_STAT
Local List
HER Number
15234
Form of Evidence
Extant Building
Sources
SOUTH TYNESIDE LOCAL LIST REVIEW 2011: REFERENCE NUMBER: LSHA/109/J
YEAR1
2012
English, British
Class
Education
COMP1
Jennifer Morrison
DAY1
14
District
S Tyneside
Easting
3312
Grid ref figure
8
LANDUSE
Building
Map Sheet
NZ36NW
MATERIAL
Brick
MONTH1
08
Grid Reference
NZ
Northing
6504
General Period
POST MEDIEVAL
Specific Period
Victorian 1837 to 1901
Place
Jarrow
Description
Opened January 1872, following the 1870 Elementary Education Act, which set the framework for schooling of all children aged 5 to 12 in England and Wales. LOCAL LIST
Site Type: Broad
School
SITEDESC
Opened January 1872, following the 1870 Elementary Education Act, which set the framework for schooling of all children aged 5 to 12 in England and Wales.
Site Name
Harold Street, St. Bede's RC Primary School
Site Type: Specific
Primary School
SITE_STAT
Local List
HER Number
15233
Form of Evidence
Extant Building
Sources
SOUTH TYNESIDE LOCAL LIST REVIEW 2011: REFERENCE NUMBER: LSHA/97/J